Train from Urumqi to Hotan (Khotan)

The train from Kashgar to Hotan officially started to carry passengers from end of June 2011. It’s total distance is 488.27 KM. The construction work started in Dec 2008 and completed Nov 2010. It goes through 10 counties before it reaches to Hotan from Kashgar. Now the starting point of the train is Urumqi and ending […]

Train from Kashgar to Hotan

According to Xinhua news agency, Kashgar to Hotan train started to transport cargo on 30th of Dec 2010, and passenger transport is expected to begin in June, according to a local official.

Train from Kashgar to Hotan

Kashgar to Hotan Train scheduled to officially operate on 10th of Dec 2010. Kashgar Hotan Railway Line is 488.27 Km long, spent of 5.073 billion yuan.The construction work began in Dec of 2008, 1st August 2009 began to pun the railway line track, and completed the putting railway track in 6th of Nov 2010.